Mountain Project Logo

Quad anchor is not redundant at the clip in point?

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129

I'd like to add this to the conversation:

http://staff.weber.edu/derekdebruin/fixedpointbelay/Comparison%20of%20Fixed%20Length%20and%20Sliding%20Anchor%20Rigging%20for%20Recreational%20Climbing%20Systems.pdf

This is a pretty realistic test set up. The result to be concerned about is the 12kN on the remaining anchor component following failure and extension of the first component. 12kN is problematic because such force breaks cams, nuts, screws, pitons, and human bodies.

The issue with the Long/Ewing and Jenks tests is that they are presented not as evidence that increased loading following extension does not occur (indeed, those data actually support that load *does* increase with extension as Mark has pointed out) but rather as evidence that extension and attendant loading doesn't matter because the loads are so small as to be irrelevant. That is indeed true for the test cases they present, but all of these test cases are <=FF1 and don't include at least two masses in the system, so of course we should expect the loads to be small. The problem is that because the loads are so small, these data become irrelevant.

The cases that matter are FF2 and near FF2, i.e. clipping an anchor component as the first piece of protection (which actually produces greater force than FF2 thanks to the pulley effect). Why are these the cases that matter? They're the ones with the most force, and they're the ones where complete anchor failure occurs (at least 6 examples of this in Yosemite in the span of 30 years, plus others elsewhere).

Dynamic rope is often asserted as the panacea to the problem, but dynamic rope in the system is of little consequence. When an anchor component fails, the secondary load after the extension happens too rapidly for the rope to "relax" and serve as the shock absorber it needs to be to keep the party attached to the mountain. This effectively causes a much higher fall factor on what could be thought of as more akin to a static rope.

In short, extension in the anchor rigging can get you and your partner killed if you fall before placing the first piece on a multipitch route.

I'll try to respond later with the pragmatic concerns about when this matters, when a quad makes sense, likelihood of an anchor component failing, etc. The risk management paradigm and the ensuing logical consequences are worthy conversation in their own right.

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129

Often, the first practical argument in favor of a quad is that knots are used to limit extension. This ends up being related to the load sharing argument, so I'll address both. There is a lower bound to how close the knots can be on a quad before they are useless, and the limit is farther than many folks think. This is because the offset of the pull angle between an aluminum carabiner and a dyneema sling needs to be about 15 degrees before the static friction between the carabiner and sling is overcome and causes the carabiner to slide. Consequently, to fulfill its proposed use case, a quad needs to have at least 30 degrees of travel in its "pocket." Other materials (ex. cord), twists, and alternative clipping schemes (capturing offset strands) all increase friction, necessitating limiting knots that are farther apart. Some folks tout the ease of pre-rigging a quad as a significant benefit and have the knots as far apart as possible (ex. Dale Remsberg noted upthread), maximizing potential extension and claiming this as a positive feature of the rigging. However, if a component fails, this extension kills the entire party. That's a hell of a gamble.

What does the spacing of knots have to do with load sharing? If the knots are too close together, the desired sliding effect can't occur (because friction) so the rigging is equivalent to a static system, albeit a very poorly constructed one. So, save the effort of tying two knots and just tie one and be done with it.

The other load sharing argument ignores the fact that in many of the test and actual use cases the sliding system and fixed system are pretty comparable for load distribution. A 60/40 split is best case for a quad (tied with dyneema). Fixed leg length static systems can get close to this, too. But in most cases, the quad doesn't perform best case, and both systems end up with spreads somewhere between 60/40 and 80/20 load splits. Consequently, the quad incurs the risk of extension and therefore total anchor failure for an uncertain (if any) gain associated with load distribution. (Skilled practitioners may also adjust the load sharing in a fixed leg anchor system with intentional construction, whether adding strands to a distant component, using a runner to make a distance component "closer," using fewer strands or position a joining knot on more marginal or nearby components, etc.)

Therefore, a sliding system really only makes sense if both components are equally terrible and neither could hold the anticipated worst case load on their own. If either of them could possibly hold the load independently, more reliable rigging would be to concentrate load on the good piece and back it up with the other. For a full explanation, see this regarding the sliding x and the attendant logical argument:

https://people.bath.ac.uk/dac33/high/6TheBelay.htm#theslidingx

However, those who warn against the quad will often say that rigging is irrelevant on two good bolts (as has already happened in this thread). Why? Because bolts are more than adequately strong and secure such that probability of failure of an anchor component is very small (though obviously not impossible). Therefore extension is not particularly relevant since the bolt won't fail, it's unlikely the carabiner comes unclipped, and the sling used to rig the quad won't get cut (because presumably no one rigs a quad, a system that is *intended* to slide, over a sharp edge). I suppose extension could happen if the sling gets cut due to rockfall, but if rock fall strikes your anchor, it's pretty likely all of it gets cut catastrophically anyway. (And yes, I know about that one guy who had rockfall cut just one leg of the two leg anchor; he's a good friend and I'm glad he's still around, but he is also incredibly lucky.)

Extension becomes relevant if the anchor components could conceivably fail. This applies to anything placed by the climber: cans, nuts, screws, pins, etc. The reason is simple: none of us is as good at evaluating a placement and/or rock/ice quality as we think we are or wish we were. There's a Spanish paper testing pro in rock and a Beverly paper for ice showing the wide variability in both the actual failure strengths of protection as well as experts' (in)ability to consistently evaluate that strength. Note that failure doesn't have to mean gear breaking. Gear can fail due to pulling for some other reason such as rock/ice failure, dirt in the crack, etc., but it might take a bit more than body weight loads to make that happen and is therefore not immediately evident.

Thus, the quad is a fine tool for bolted anchors and ill suited for other applications given the straightforward cost-benefit tradeoff.

Citations for much of the above can be found in the references section of the paper I posted upthread. Further reading with a pretty solid signal-to-noise ratio that's worth the time:
https://www.mountainproject.com/forum/topic/113456950/new-aac-article-on-anchors

@Nick: I'm most wary of the quad on ice compared to other media, given the extremely variable and unpredictable nature of ice coupled with the potential for long runouts, especially off the belay (depending on one's proclivities). I'd strongly encourage you to consider the banshee belay as an option that still allows for pre-rigging, doesn't require tying/untying knots (though some styles require a clove hitch), and is still versatile and easy for ice. The simplest version of it is simply one ice screw as the focal point and then a single alpine draw to a second screw above (and offset to the side to avoid the orthogonal fracture planes of ice). Very fast and easy to rig for both leader and follower, even using the fattest gloves I own.

Mark Pilate · · MN · Joined Jun 2013 · Points: 25

Fuckin A.  Derek it’s a pleasure to have you in this thread. 

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129
Mark Pilate wrote:

Fuckin A.  Derek it’s a pleasure to have you in this thread. 

Hahaha. Thanks. I might just clean this up and turn it into a blog post some time so it can be readily referenced in the future.

Also, I know I made some fairly strong assertions (though backed by evidence), but I mean nothing personal toward anyone in the thread. Honestly, I'm just trying to move away from potential misinformation/misunderstanding so folks can make fully informed decisions. I'm a big fan of strong opinions that are weakly held, so if folks have other stuff to offer on the subject, I'm happy to hear it.

Bruno Schull · · Unknown Hometown · Joined Dec 2009 · Points: 0

@ Derek--I really appreciate that contribution.  Thank you so much.  The power of your ideas, and your ability to express these ideas, is superb.  You should definitely synthezise those posts into some kind of statement of sticky, and distribute that in the world.  All the best.  

DrRockso RRG · · Red River Gorge, KY · Joined Sep 2013 · Points: 1,379

Derek, without swathing through all that info you referenced,  where are you finding that traditionally equalized anchors are likely to load share as well as a quad, or that a quad is likely to load share 80/20?

Mark Pilate · · MN · Joined Jun 2013 · Points: 25

DrRockso, a “meta analysis” of most of the papers and data published do show that a quad “equalizes” better than a fixed point, but really to a mostly trivial level of percentages in lab tests.

I just re-ran some of my own quick tests down in my own “lab” in the course of this thread and it was around ~9% better load delta distribution for 30 degree load shift (100 lb load) using dyneema  (Quad vs fixed masterpoint, N=5 each).   Not nearly enough to warrant the risk.  You don’t get that adjustment benefit in sudden force application of a fall, just the shock load risk  

Plus, as shown in the Dale Remsberg pic example, the way quads are typically used with opposite pulls from the two people at a stance, the “equalization” gets negated and it’s equivalent to if there was a fixed point essentially where the two sliding points cross.  

You do get a damped transfer of movement from either side though.  Not enough in my book to make up for risk on nuts and cams, etc.  after all, the rock or crack does not have a CE/UIAA rating, and is a mystery and left to good judgment and experience.  

I wholeheartedly agree with one of your previous points that focusing on teaching solid anchor placements is the key.   The goal here is to clarify some misunderstandings and eliminate some false assumptions so people can make the best decision at the time. 

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129
DrRockso RRG wrote:

Derek, without swathing through all that info you referenced,  where are you finding that traditionally equalized anchors are likely to load share as well as a quad, or that a quad is likely to load share 80/20?

I don't know of a comprehensive meta analysis (though this is probably a topic deserving of one in the sense that it would be low hanging fruit). I believe it's rigging for rescue (or maybe SAR3?) that has lots of data on load distributing systems (slow pull testing), both fixed length and sliding, with all kinds of riggings. There's a paper done by Tom Evans (I think?) that looks at failure of an anchor component with rescue loads. Even the DMM videos provide comparative data for relative loading (even if the numbers themselves aren't particularly useful given the solid masses and lack of rope in the tests). The CAI has drop testing data, as well as the DAV and a small amount from ENSA (most of which is not in English). Most/all of these are in the references for the paper I linked. A number of other references are included in the comments near the bottom of the page for the below article (search for comment by Ron Funderburke). You can also find a number of one-off tests Jim Titt has done and posted in these forums.

https://americanalpineclub.org/resources-blog/2017/7/31/anchors

Before going farther, I want to emphasize again that the drop test at FF2/near FF2 is the one that matters as it produces loads of concern (since previous testing makes clear that lower FF doesn't produce high enough loads to be problematic). In a leader fall, the force that dominates is gravity, so the vector of pull is always net down. However, depending on where the leader is when they fall, the load typically comes from one side or the other (it would be a rare fall for the leader to come straight down since typically they would typically be landing on the belayer). Consequently, if using two load cells with high speed data collection, the comparative load often settles to something similar to what's seen in slow pull tests. However, the initial load can be multiples larger on one anchor point compared to the other based on where the carabiner sits, the belayer is at, which side the leader fell from, etc.

I wouldn't say an 80/20 is "likely" with a quad (and if I literally said that I'll go back and edit it), but it is certainly possible for the holding the initial fall. I think of it like this: the load distribution between two points in an anchor is likely Gaussian (aka normal distribution/bell curve) for a sliding system and a fixed system. The measure of central tendency for the fixed system will be shifted toward less equal load distribution compared to a sliding system, and at the tails, the sliding system with be closer to the goal of 50/50. But there will be significant overlap in the middle between the two options (probably about 3 or 4z I'd guess), and you're likely on target for 65/35 split in either case a lot of the time. (See below for a not-to-scale and purely hypothetical visualization of what I mean.) For example, a vertical crack with a fixed anchor will get you close to that (and will get you roughly 60/30/10 split with 3 pieces). Most of the time, I don't think there will be a substantive or field-reliable difference for a competent anchor builder.

Consequently, this gets back to whether it is of value to attempt to reduce the load to any given piece by distributing the load in the first place. If you don't clip a piece of the anchor as the first piece of gear (and didn't rip a piece out of the anchor and therefore cause extension), you're looking at max loads around 6kN (maybe 7). If you check out the link to the multipitch climbing site I posted above, you can see why it's probably not worth worrying to much about load distribution at all. Practically speaking, I'll often still attempt load distribution to some extent. That's simply because distribution likely improves the probability that I won't rip my anchor out of the wall and we have simple rigging options that do a decent (if imperfect) job of this.

John M · · Unknown Hometown · Joined Jul 2014 · Points: 321

Dumb question: isn't clipping 3 strands of the quad the same thing as clipping 1? In the load test videos of the quad, with 3 strands clipped, when one leg blows, the master biner slides down to the limiter knot, then the knot pops through the biner, and the biner ends up on the single-strand side. (Then, when loaded again, that single strand tends to snap at one of the limiter knots.) 

Wouldn't it make more sense to clip 2 strands as a general rule?

rocknice2 · · Montreal, QC · Joined Nov 2006 · Points: 3,847
John M wrote:

Dumb question: isn't clipping 3 strands of the quad the same thing as clipping 1? In the load test videos of the quad, with 3 strands clipped, when one leg blows, the master biner slides down to the limiter knot, then the knot pops through the biner, and the biner ends up on the single-strand side. (Then, when loaded again, that single strand tends to snap at one of the limiter knots.) 

Wouldn't it make more sense to clip 2 strands as a general rule?

Because when that single strand blows the whole thing is junk.

Yes clipping 2 strands make the most sense. If using a quad makes sense to you.

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129

Amalgamated some of my thoughts from this thread and added a few other ideas into a quad explainer for those who are interested:

https://staff.weber.edu/derekdebruin/fixedpointbelay/The%20Quad.pdf

Mr Rogers · · Pollock Pines & Bay Area CA · Joined Dec 2020 · Points: 15
Derek DeBruin wrote:

Amalgamated some of my thoughts from this thread and added a few other ideas into a quad explainer for those who are interested:

https://staff.weber.edu/derekdebruin/fixedpointbelay/The%20Quad.pdf

good stuff.

DrRockso RRG · · Red River Gorge, KY · Joined Sep 2013 · Points: 1,379
Derek DeBruin wrote:

Amalgamated some of my thoughts from this thread and added a few other ideas into a quad explainer for those who are interested:

https://staff.weber.edu/derekdebruin/fixedpointbelay/The%20Quad.pdf

Seems like your bell curve chart isn't based on any real world data. My experience is that I regularly see people tie 2, 3 and 4 peice prequalized anchors where 1 peice is taking a 100% or close to a 100% of the load and the other peices are merely acting as backups. It's certainly more than 1% of the real world examples I see. It's not a deal breaker for me,  but I think it's unfair to assume that the vast majority of folks prequalized anchors are seeing meaningful load sharing.

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129
DrRockso RRG wrote:

Seems like your bell curve chart isn't based on any real world data.

True. I did state that it was purely hypothetical and meant to illustrate the bigger concept of the significant overlap between the systems with regard to load sharing. I don't know of any such data, and collection would be onerous, if not impossible. I couldn't just recruit folks to tie anchors without biasing them toward being on their best anchor building behavior so to speak, but it also probably wouldn't work well to hang off a static line as folks arrive at a belay to say, "So, before you clip into that, I'm just gonna install these load cells..." 

Just the same, I hope the purpose of the chart was clear and not confusing. 

My experience is that I regularly see people tie 2, 3 and 4 peice prequalized anchors where 1 peice is taking a 100% or close to a 100% of the load and the other peices are merely acting as backups. It's certainly more than 1% of the real world examples I see. It's not a deal breaker for me,  but I think it's unfair to assume that the vast majority of folks prequalized anchors are seeing meaningful load sharing.

Fair point. Without data we are left with anecdote, but I don't doubt you. Maybe I was being too generous in assuming folks could tie a knot and pull down on it. But, to me that also seems a much more fundamental skill. And as I state in the section on risk management, and as others have agreed (you as well, I think? I'd have to go look), the bigger skills are belaying, placing solid gear, climbing well, etc. In that sense, if you're at a point where the concerns of load sharing and extension are on your radar because you've mastered those other fundamentals, I'd hope you could tie a knot effectively. I'm not even going to pretend that my climbing partners represent an unbiased sample, so I really don't know.

Mark Pilate · · MN · Joined Jun 2013 · Points: 25

Don’t need to hang out at multi-pitch belays, Might set up just such an example to collect that kind of comparison data at the local gym.  Set up some example 3-4 piece anchor points with all load cells feeding into a computer and have numerous volunteers tie both LS and LD anchors and compare results.  Can also plot results against years of experience to see if veterans are statistically better than noobs 

Tom Sherman · · Austin, TX · Joined Feb 2013 · Points: 433

Guess I’m trolling?!?! But seriously:


I’ve known about and understood the quad anchor for ~8 years??? I’ve never felt there was a purpose for using one.

If you’re one of those people who goes out and buys a PAS (failing to come up with other examples) etc… probably a great knot for you. It’s a niche, gadgety, tool, for a single-use application, that its means can be accomplished a multitude of other ways with the standard climbing gear on your harness. It offers no advantage other than convenience in the form of telling your brain “I do the clip, clip the thing to the anchor, when I do…”. People who need an item to be a solution to a scenario, the quad is perfect for. It’s also humorous because it’s for non-advancing sport climbers! The quad has no application outside of sport climbing or top roping.

Did I get something wrong?

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129
Mark Pilate wrote:

Don’t need to hang out at multi-pitch belays, Might set up just such an example to collect that kind of comparison data at the local gym.  Set up some example 3-4 piece anchor points with all load cells feeding into a computer and have numerous volunteers tie both LS and LD anchors and compare results.  Can also plot results against years of experience to see if veterans are statistically better than noobs 

Thought about that, but don't you think the very nature of that experiment creates bias that will no longer meet the real-world criteria? I have to imagine that if I ask folks to tie anchors in a gym for a study they'll be doing their very best, when in the field they might indeed just leave the single piece getting most of the load as Rockso describes and call it "good enough." 

DrRockso RRG · · Red River Gorge, KY · Joined Sep 2013 · Points: 1,379

I think even the data from what you describe would be skewed Mark, both because people would be hyper aware of getting the equalization just right vs real life (hopefully you're not telling them what the purpose of the study is, though if they see you putting load cells in it might be pretty obvious for some) and the fact that the direction of load is often changing,  the belayer is not always weighting the rope in the exact direction the follower is falling and likewise the leader might factor 2 onto the anchor from different directions as they climb up a diagonal crack for example.  

Derek  I 100% agree there are more important things to focus on. 

Tom, go climb a 20 pitch route with all bolted anchors and mostly all hanging belays somewhere like Potrero Chico, and then do the 20 rappells down.  The quad is pretty awesome for things like this,  40 less anchors to tie and untie. 

Derek DeBruin · · Unknown Hometown · Joined Jul 2010 · Points: 1,129
Walt Dog wrote:

Weird that guides teach this highly dangerous anchor…. I mean it’s not like they know anything about best practices 

I’ll just leave this here

Thanks for chiming in. I'll let Rockso (a guide) and Mark (former guide) share more about themselves if they wish, but if what you meant was to ask about my credentials I'd be happy to share. If not, then frankly this isn't helpful.

I'm a certified AMGA Rock Guide. I teach the AMGA's Single Pitch Instructor program. I also teach climbing at a university. I've presented on a variety of topics and audiences at the AMGA Annual Meeting every year for the last 7 years. I've authored articles for the AAC's education program. And since I'm not just some science nerd who doesn't do anything in the real world, sometimes, I even go climbing. Outside.

"Danger" is an interesting idea, since it's all relative. I mean, it's not like climbing itself isn't dangerous and it's amazing it hasn't been outlawed completely and guides can teach it at all. In many cases a quad is acceptable, but the danger comes from a low probability edge case. Does that make it "highly" dangerous? That really depends on how danger is being defined in relation to something else.

From a systems risk management perspective, low probability high consequence hazards would be better managed by a default selection that can handle those edge cases, which is really the crux of this discussion. 

Finally, just because one is a guide doesn't mean they're infallible or actually have the best practices. Guides have been wrong before (the kreuzsicherung comes to mind as one example) and everyone is still subject to their individual and/or collective biases. Plus, guiding itself is biased toward certain techniques. Guides tend to like masterpoints and plaquettes, so their clients often end up learning and mimicking these techniques, even if they're not strictly required for recreational climbing. In short, guides can (and absolutely are) wrong sometimes. And that's okay. We can collectively question existing methods, consider new ones, study them, and change techniques accordingly. That's how we make progress. 

Edit to add:

Rockso, we definitely agree on the two bolt anchors. Getting sendy in Potrero on nice 2 bolt anchors for 20 pitches is a great application for the quad in my opinion. 

Jim Titt · · Germany · Joined Nov 2009 · Points: 490
Derek DeBruin wrote:

Thought about that, but don't you think the very nature of that experiment creates bias that will no longer meet the real-world criteria? I have to imagine that if I ask folks to tie anchors in a gym for a study they'll be doing their very best, when in the field they might indeed just leave the single piece getting most of the load as Rockso describes and call it "good enough." 

We did a study mabe 10 years ago as part of the "equalisation is a myth" project and even with unconcious bias the results were truly appalling. We asked random climbers to rig multi-piece anchors in pieces we'd already placed all over the place (not the nice textbook group) and outdoors where visual clues are lacking. 

Most commonly the centre piece in 3 piece anchors saw no load, with 4 piece mostly 2 random legs saw no load. 80-20 on the remaining was normal. Basically you have to expect only one piece is being loaded at any one time.

Guideline #1: Don't be a jerk.

General Climbing
Post a Reply to "Quad anchor is not redundant at the clip in point?"

Log In to Reply
Welcome

Join the Community! It's FREE

Already have an account? Login to close this notice.