cooling tower project
|
Jim Titt wrote: Hi, the cooling tower has a thickness of 30 cm in the basement. The thickness of the concrete is less in higher altitudes (131 m height). The regulations for cooling towers in germanyy are the use of at least B35 concrete nowadays. Nevertheless i will test each anchor with the Hilti HAT28. Thanks for your replyFrank |
|
A Little update, Thank you for the given tips. Many greetings Frank |
|
Frank Niehus wrote: A Little update, The steel plate should have been on the outside, in this configuration it serves no purpose. |
|
Tradiban wrote: Hmmm..... You don´t do much of this kind of engineering do you? That´s almost exactly what I would have built, maybe with a stiffening web horizontally but mostly I wouldn´t bother, just pick up a thicker bit of plate instead as welding costs more than steel. Wouldn´t have bothered with the hangers and dogbones though, "refined" design in 8mm plate or crude in 10mm would be fine. |
|
Frank Niehus wrote: A Little update, Pretty neat setup and interesting video. Thanks for the follow up. |
|
Jim Titt wrote: I missed that the connection is on the plate since there's a mess of limp webbing as backup. So, four 3/8 bolts within 6in of each other with no backing is what is holding this thing? Don't call me when the crete blows out with all four bolts still attached. |
|
4 x 10mm SS wedge bolts 60mm embedment, C20/25 concrete = 4 x 10.7kN = 42.8kN working load. The typical failure would be over 64kN and I'd expect to see up to 150kN. |
|
Jim Titt wrote: 4 x 10mm SS wedge bolts 60mm embedment, C20/25 concrete = 4 x 10.7kN = 42.8kN working load. The typical failure would be over 64kN and I'd expect to see up to 150kN. Ya, if they were floor anchors. |
|
Jim Titt wrote: 4 x 10mm SS wedge bolts 60mm embedment, C20/25 concrete = 4 x 10.7kN = 42.8kN working load. The typical failure would be over 64kN and I'd expect to see up to 150kN.I have concrete failure on a 6" by 8" anchor pattern at about 12k (50ish KN) assuming 12" (30cm) concrete that the OP indicated. Thanks for giving me something to do this afternoon! |
|
Tradiban wrote: What are you on about? I'd expect to see 25kN+ axial for each of those bolts in C25 concrete and 35kN+ in something really good. I test maybe 100 a year in concrete to certify the things. |
|
Jim Titt wrote: Real world is a lil' different than the lab. |
|
Whatever. |
|
Tradiban wrote: Hi, the steel plate setup has worked fine for us. Anyway, on the picture you see two green loops, who are connected with the outside of the cooling tower through a bolt in different concrete sections. I do not think it was really needed, but it was reassuring to have this two backup lines if the system would have failed.Many greetings Frank |
|
Jim Titt wrote: Hi, we used a 8 mm steel plate as a base. The "Singing Rock" backup loops are probably unnecessary but we felt a little bit safer with it. Anyway, there are always things you could improve. Thank you very much for the given feedbacks during this project from an expert like you. P.S. I really like your products, especially the "Rod Belay Hanger".Many greetings Frank |
|
Corey Day wrote: Thank you for the positive feedback. Many greetingsFrank |
|
Frank Niehus wrote: I don't doubt ithas worked fine, your project wouldn't produce much force based on the vid. The point is that a force capable of breaking the hardware would surely break the webbing in quick succession.If a huge force were able to be produced I contend it would rip the whole unit plate included with a chunk of the wall along with it. |