The primary steel should be done today and yes it will take about three-four more weeks to get the secondary steel, mezzanines, insulation, walls,roof, windows, skylights, etc installed. Other trades should be back in the building in two weeks. The first shipment of climbing walls arrives in early Sept. Current thinking is that there will be a soft opening in early November, with the whole gym being ready about a week later. The bouldering area is the last to be installed (it worked out that way because of the layout of the building, all the bouldering -excluding systems boards- is in that north "shed" with the roll up doors.)Latest stats on the climbing wall: 28,400 sq. ft. with 2000 sq ft of 3-D walls (mostly in the bouldering cave).