So I've tried searching, but am not sure what to even search for with my questions. |
|
Have you seen the presewn anchor slings? all it is is just a length of nylon or dyneema webbing with two loops sewn at the end.. that would definitely help (i want to get one myself). also, i myself wouldn't call off belay until i have atleast two pieces in.. i like redundancy. this is only on exposed/hanging belays though. i will yell off belay with one piece in on a secure belay platform. thats just me. im sure theres some way better tips out there. |
|
Fuck the pre sewn slings and alpine equalizer. Less is more! I've spent a great deal of time tweaking my setup, which is a 20' piece of cordalette. I use Titan cord which I like for its rigidity, and I'm not sure, but I believe it's 5mil. I have tied a figure eight on a bight at each end. I found this to be the most versatile setup. As far as setting up, I usually place the first piece, and if its bomber, then I clove my rope to it then I'm off belay. That gives me time to build anchor while partner begins to clean previous anchor. If its not bomber, then make the 3 point equalized anchor then clove to master then off belay. My 2cents... |
|
Screw all that stuff. Use your rope and some clove hitches. Saves weight, saves time and it is bomber. |
|
The most important thing to realize is that there are "best practices" for different scenarios. There is no "one ring to rule them all" belay building style. What works really well for one area and team might be terrible for another climbing venue. You have to think for yourself and modify systems to your needs. I ended up tying my own to test the idea out. After a few days out with it I REALLY liked the setup. It's FAST to implement, provides a clear "master point" and is damn simple for the second to breakdown and stow (just like and over the shoulder sling). It's also less bulky than a cordalette. I ended up ordering the edelrid adjustable one . Here's Edelrids video (german) of it in multiple setups. vimeo.com/47001108 Again, you need to determine WHAT your needs and preferences are. There's no silver bullet. Right now, for me, the Belay Sling is damn useful. |
|
I think it really comes down to "practice makes perfect"...or something like that. The faster you can recognize what it will take to build an anchor upon reaching the end of a pitch, the quicker it will go up. In other words, if you finish your lead and instantly know that the crack in front of you will take a .75BD, a #1 Mastercam, and a #6 stopper, you're already saving minutes of debate time. |
|
cjon3s wrote:Is it best to clip the first piece and just take and then set up the rest of it?So you're thinking you'll clip in to/put weight on a single piece? That ain't an anchor in MY book. |
|
cjon3s wrote:So I've tried searching, but am not sure what to even search for with my questions. Here goes: I'm looking to be a bit more efficient with my cordelette setup. So does anyone have recommendations on their order of operations when setting up the cordelette? Is it best to clip the first piece and just take and then set up the rest of it? What about going in direct to a solid first piece? Maybe a sling to a solid cam or a clove hitch, then call off belay and finish the anchor while the second prepares to move. I'm just looking for a system that would be the simplest, most direct way to do this. I've tried both of these and I feel almost like I'm fumbling trying to move things around to get my cordelette setup around the rope. Thanks for the suggestions!------------------------------ I hate to be harsh, but if you have to ask this question on the internet (on Mountain Project of all places) you need to pay an AMGA certified guide for a day's lesson before you become rescue bait. Time-wise ...you should have this down in less than a minute unless the gear placements are extremely tricky. Is this another troll? |
|
It wasn't a troll. My main issue more than anything was keeping my rope out of the way of my cordelette when constructing my anchor. I was clipping my cordelette and rope to the same biner. |
|
Any suggestions on what you guys use for block leads? |
|
Block Leading
I have no issue using the rope to anchor when swapping leads, but the cordelette makes more sense for block leading. Are there any other, possibly better methods you all use? ----------------------------------------------- My priority is now get up the route as fast as possible in good style I use whatever's left on my rack at the top of the pitch. Hopefully it will not be a vital piece for the next pitch; that's my selection criteria. The same selection process for rigging. If the next pitch is going to take a lot of long runners, I limit my use in the anchor; if not I may be use 2 runners. Everything comes to a master point (power point). I might be temporarily clipped (hitch or figure 8...doesn't matter...if you have trouble clipping a clove hitch in then you need practice or wider biner gates) into a piece (more than likely my first placement if I am pumped or the stance is fully hanging). It's a belay anchor so by definition every piece should be bomber. It's my discretion to yell down "off belay" or "I'm in direct". I've discussed what this means prior to climbing with my partner. If I am guiding, I say nothing till the anchor is complete. With a cam, I'll add a biner to that sling (With a bolt hanger I'll add a carabiner under my clip or girth hitch a sling to the hanger.) and go on fashioning the anchor. If the placements are straightforward this process should take less than 60 seconds to where I can safely say "off belay". After, I may refashion the belay while my partner is clearing the lower station to the final piece. Frankly, I seldom carry a cordelette. Seldom being maybe 3 times in 10 years. I average about 120 days or more a year climbing. If I was professionally guiding parties of 2, I might because clients seem to visualize a cordelette set up quicker. You could purchase Criag Lubben's book on anchors from Amazon books. It has useful information. Alternately you could hire a guide for a day. All AMGA guides will be well schooled in multiple ways how to set safe equalized anchors efficiently. If your partners are giving you the "stink eye" and criticizing your anchors then the guide is the way to go before we read about your tragic accident here. |
|
I'm not going to kill myself. I'm asking alternatives to what I do, a cordelette, which is in no way unsafe. Obviously we aren't on the same page here as you described parts of anchor and what you do when building it without actually explaining what the anchor is... are we talking sliding x's? Just tied off with an 8? Is your anchor setup different for each pitch accordingly then? Or is there one systematic approach for each anchor? |
|
This is a topic about which folks have lots of differing opinions. There is not one RIGHT way to make an anchor, but there are a lot of ways to do it that are not very efficient, or even safe. |
|
for block leading i just use a cordelette or a long sling and built a simple masterpoint for gear anchors |
|
Me, when not anchoring with rope, which you didn;t ask about.... |
|
The seriously best idea in this thread: "dont worry about everyone on the intraweb telling you about how you MUST use their pet technique or youre a gumbie ..." |
|
Rhett Burroughs wrote:Me, when not anchoring with rope, which you didn;t ask about.... Arrive at leadge, get good first piece, clip into it with a runner, weight it, stay on belay. Place addiitonal two pieces, clip my cordalette or webolette thru all three, pull down a masterpoint in the direction of climber/weight, tie an overhand or fig eight, clip locker to master point, double check the anchor, yank on the anchor, while still on belay. Clove to masterpoint locker with rope, weight/pull on knot to cinch it at agreeable length, unclip from first piece, and go off belay. This, is the easiest way to work a cordalette and leaves you with a hanging runner for your second or for your gear. If climbing with one partner, we always just throw a clove each on the masterpoint. With a party of three, if doing a route with belays on decent ledges, if everyone girth hitches a sling or PAS with locker, everyone clips into the masterpoint locker with their locker. Not dynamic, but this keeps the rope free for stacking and doesn't clog up the masterpoint. Just don't unclip your buddies biner. Back any of these up with additional slings or rope to your comfort level.Sorry that I phrased my question so poorly but thisnis exactly what I was looking for! The extra runner helps keep everything neat and keeps my rope and cordelette separate which keeps me from tangling the two during setup. I actually just tried it out at the gym off of some draws and it worked flawlessly. Thanks a lot. |
|
Daniel Evans wrote:How do you build a gear anchor with your climbing rope? Are there any diagrams/videos out there that would effectively demonstrate it? My climbing partner was a mountain leader course instructor with the Marine Corps at MWTC Bridgeport, CA for 3 years and I'm taking AMGA private guide sessions and I have never heard of this. I've always just used a cordalette equalized to three pieces of gear. Or maybe I misread some of your comments and your referring to using the climbing rope as a PAS which I am familiar with.See here That's one method. User rgold has a very similiar setup which he came out with previous to this. It can easily be found with a google search. It's also possible to clove three pieces together and adjust the tension so they share the load. You could even set it up just like a cordelette. Clove the two outer pieces leaving a good amount of slack, clip the middle piece, then pull down the two loops you've created and tie a masterpoint. There are a ton of different ways to do this along with appropriate situations. In my case, block leading, it's a bit less convenient than just using a cordelette. But, it does only take a minute or two to switch the anchor to the followers side of the rope when block lead. I just find the cordelette works better for me. |
|
And... deleted his post... |
|
hey ya sorry, deleted my post cause I stumbled upon another thread that had videos & diagrams. ha my bad. but thanks for the reply. |
|
Actually hey thanks a lot. That's the best video I've seen. Looks pretty legit, I'll have to practice that my next guide session, appreciate it. |